Pre-Construction Decision Guide

What to Review Before Signing a Construction Contract

Before signing, confirm that the contract and every referenced document describe the same project: scope, price, allowances, exclusions, schedule, payment milestones, change procedures, owner responsibilities, warranty, and completion standards.

Metro Atlanta guidance for custom homes, additions, and major renovations.

Direct Answer

Review the agreement as a connected project system—not as a single document.

A construction contract may incorporate drawings, specifications, proposals, allowances, schedules, exhibits, and builder standards. If those materials conflict or leave decisions open, the homeowner may not have a reliable picture of what is included.

Start by confirming the contracting parties and project address. Then trace the scope, selections, price, payment schedule, change process, completion requirements, insurance, warranty, and termination provisions across every referenced document.

Contract review has two different jobs.

Project and scope review asks whether the documents accurately describe the intended build and whether responsibilities, assumptions, allowances, and exclusions are organized clearly.

Legal review asks what the agreement means under applicable law and evaluates rights, remedies, liability, dispute terms, and enforceability. RCC does not provide legal advice; consult a qualified attorney before signing.

12-Point Review

The construction contract checklist

Each item should be clear enough that the homeowner, builder, design team, and attorney can identify the same obligation and supporting document.

Parties and project identity

Confirm legal names, business entity, license holder or qualifying agent, project address, owner names, notice addresses, and authorized representatives.

Complete document list

List every drawing, specification, proposal, exhibit, addendum, selection schedule, and builder standard incorporated into the agreement—with dates and versions.

Scope of work

Verify what the builder will furnish, coordinate, install, supervise, permit, test, and complete. Match the language to the final plans and proposal.

Exclusions and owner-supplied items

Identify work, materials, fees, utilities, site conditions, design services, and specialty items that remain outside the builder’s responsibility.

Contract price and pricing method

Understand whether pricing is fixed, cost-plus, or another structure; what the fee covers; and which items can change the amount.

Allowances and selections

Record each allowance amount, what it includes, markup treatment, selection deadline, pricing source, and how overages or credits will be calculated.

Schedule and extensions

Define commencement conditions, target milestones, substantial completion, final completion, owner decision deadlines, and permitted extensions.

Payment and draw process

Connect each payment to defined progress, documentation, review timing, retainage if applicable, and the process for disputed amounts.

Changes and written authorization

Clarify who may request or approve a change, required cost and schedule information, markup, and whether work may begin before written approval.

Site, access, and owner duties

Identify responsibilities for surveys, utilities, financing, access, temporary facilities, selections, design decisions, insurance, and owner vendors.

Completion and closeout

Define substantial completion, punch-list handling, final completion, occupancy documents, manuals, warranties, releases, and final payment conditions.

Warranty, disputes, and termination

Locate warranty coverage and exclusions, notice procedures, correction process, dispute path, suspension rights, termination provisions, and governing law for attorney review.

Document Control

Documents to assemble before the contract is final

A complete review requires the current version of every document that affects scope, cost, schedule, or responsibility.

Project and pricing documents

  • Final builder proposal and estimate detail
  • Issued drawings and specifications
  • Allowance and selection schedule
  • Written exclusions and assumptions
  • Alternates, options, and accepted revisions
  • Preliminary construction schedule

Business and closeout documents

  • License and business-entity information
  • Current insurance certificates
  • Payment or draw schedule
  • Change-order form and markup schedule
  • Written warranty document
  • Sample closeout and final-payment requirements

Cross-Document Test

Make the proposal, plans, and contract agree

The review is not finished when each document looks reasonable by itself. Compare the same decision across the full set.

DecisionWhere to checkQuestion to resolve
Project scopeContract, proposal, plans, specificationsDo the documents describe the same work and quality level?
PriceContract sum, estimate, alternates, allowancesWhich amounts are firm, estimated, or still owner-dependent?
SelectionsAllowance schedule, specifications, finish schedulesWhat remains undecided, by when, and with what budget?
ScheduleContract dates, milestone schedule, selection deadlinesWhat must happen before work starts and what can extend time?
PaymentsDraw schedule, milestone definitions, closeout listWhat evidence supports each payment and final payment?
ChangesContract clause, change form, markup termsWho approves price and time before changed work begins?
CompletionDefinitions, punch list, warranty, occupancy documentsWhat distinguishes substantial completion from final completion?

Resolve Before Signing

Six questions that deserve a written answer

Which document controls?

If the contract, drawings, specifications, or proposal conflict, the agreement should identify how the conflict will be resolved.

What is still undecided?

Create one list of open selections, design items, allowances, site questions, and owner-supplied products.

What changes the price?

Separate known scope from allowances, contingencies, unit prices, unknown conditions, and owner changes.

What changes the schedule?

Identify dependencies tied to permits, financing, design completion, selections, site conditions, weather, and change orders.

What supports each draw?

Connect payments to defined progress and determine what documentation will accompany each request.

What completes the project?

Define occupancy, substantial completion, punch work, final documentation, warranty delivery, and final payment.

A Practical Sequence

How to organize the review

Collect

Assemble the proposed agreement and every incorporated document, using current dated versions.

Map

Create one list of scope, price, allowance, schedule, payment, change, and closeout provisions.

Compare

Cross-check the contract against the final proposal, plans, specifications, and accepted decisions.

Resolve

Ask the builder and design team to document clarifications, missing decisions, and agreed revisions.

Review legally

Have a qualified attorney evaluate legal rights, remedies, liability, dispute, and termination terms before signing.

RCC’s Role

Project clarity and legal advice are different responsibilities.

Your builder represents the build. RCC represents you—while working collaboratively with the professionals responsible for design, construction, inspection, engineering, and law.

RCC can help homeowners

  • Organize the contract and incorporated documents
  • Compare scope against proposals, plans, and specifications
  • Identify allowances, exclusions, assumptions, and open decisions
  • Prepare project questions for the builder and design team
  • Coordinate project information for qualified legal review

RCC does not replace

  • A qualified attorney providing legal advice
  • The builder’s contractual construction responsibilities
  • Architectural or engineering design services
  • Code officials or independent inspectors
  • The homeowner’s final approval and signature decision

This educational guide is not legal advice and does not interpret any specific contract. Construction agreements and project circumstances vary. Consult a qualified attorney licensed in the applicable jurisdiction before signing.

Georgia Resources

Verify information through official sources

Georgia Consumer Protection Division

Georgia’s homeowner guidance recommends written estimates based on identical project specifications and a written contract addressing scope, dates, total cost, and warranties.

Read Georgia homeowner guidance →

Georgia contractor licensing

Use the Secretary of State’s official resources to review residential contractor licensing information and access license-search tools.

Review licensing resources →

Homeowner Questions

Construction contract review FAQs

Should I sign if the drawings or selections are not finished?

First identify exactly what remains incomplete and how those open items can affect scope, price, and schedule. Ask the builder and design team to document the treatment of unfinished information, and obtain legal advice before signing.

Is the proposal part of the contract?

Only the agreement and its incorporated documents can answer that. Confirm that the final dated proposal is expressly included—or that its scope is fully carried into the contract documents—and ask an attorney to evaluate the legal effect.

What should an allowance state?

At minimum, identify the item, budget amount, what costs are included, selection deadline, pricing source, markup treatment, and how overages or credits are calculated.

How should change orders work?

The documents should identify who can approve changes, what cost and schedule information is required, applicable markup, and whether changed work may proceed before written authorization.

Can RCC provide legal contract review?

No. RCC can organize project and scope information, identify questions, and help prepare the document set. A qualified attorney should provide legal interpretation and advice.

When should I complete the Build Risk Assessment™?

Complete it before signing or whenever major project decisions remain unresolved. It helps identify which scope, team, budget, documentation, and oversight questions deserve attention next.

Reviewed for RCC homeowner education • Updated August 28, 2026

Before You Sign

Find the project questions that deserve attention now.

The free Build Risk Assessment™ helps homeowners organize unresolved decisions across scope, team, budget, documents, and project oversight.

Start the Free Build Risk Assessment™
Start the Build Risk Assessment™